Project
Parkwood Southlands Phase 1
Fort St. John, BC
CLIENT
XJ Evergreen Estates Corp.
VALUE
$2.6M
DURATION
May 2021 - November 2022
Project Scope
- Construct to MMCD Specifications
- Installation of 600 m of 600 mm sanitary manholes
- Installation of 250 m of 525 mm sanitary manholes and future stub outs
- Install 550 plus meters of 375 mm and 300 mm storm manholes, headwalls and catch basins
- Install 225 m of 300 mm water line and 3 Fire Hydrants and 2 Future service extensions
- Electrical included installation of BCH/TELUS and Shaw conduit and service box installs and light standard and light poles
- Complete road subgrade construction, granular hauling and compaction, pavement, curb and sidewalks
- Landscape – install root barriers and topsoil
Roles & Responsibilities
- Pre-construction meeting with the Main Contractor and the Owner
- Weekly meetings and progress updates
- Updates when required to the Main Contractor/Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
- Quality management updates and quality control check sheets of construction progress and material installs
- Coordination with other subcontractors to complete project works
- Site inspections with the Main Contractor/Owner
High Impact Result
As a local company it was an honor to complete Parkwood Drive which will be the main entry way to Fort St. John’s newest and largest master planned community.
Subcontractor(s)
Ironhide Contracting, DGS Astro Paving Ltd, Boreal Pacific Enterprises, Lazer Pavement Solutions, Metro Testing & Engineering
Let’s get your project off the ground!
From site preparation and underground utilities to road building and large-scale infrastructure work, our team will work with you to deliver practical solutions that align with your goals, timeline, and budget.
Start a Conversation