Meziadin Pipe Push

CLIENT
DRM
VALUE
$2.3M
DURATION
Sep 2025-Nov 2025

Project Scope

West of Surprise Pit – based on an 10 day pipe installation, 22 day total on site

  • Build access inlet side, create bypass pumping pad, entrance pit (trucking of spoil and supply of granular by DRM)
  • Build access outlet side, receiving pit, realign channel (trucking of spoil and supply of granular by DRM)
  • Rip Rap placement, inlet and outlet (supply/delivery by DRM)
  • Grout Abandoned Culvert
  • Bypass Water Pumping
  • Supply & Install 60” x 36m pipe

Lakeview Corner – based on an 10 day pipe installation, 22 day total on site

  • Build access inlet side, create bypass pumping pad, entrance pit (trucking of spoil and supply of granular by DRM)
  • Build access outlet side, receiving pit, realign channel (trucking of spoil and supply of granular by DRM)
  • Rip Rap placement, inlet and outlet (supply/delivery by DRM)
  • Grout Abandoned Culvert
  • Bypass Water Pumping
  • Supply & Install 72” x 45m pipe

Roles & Responsibilities

Challenge

Limited geology showing fill and rock formation, potential challenge in installation rate and risk of encountering boulder and large size rock

ACL Solution

Up size the gauge of the steel culvert in case structures were encountered

Highlight / Achievement

Both replacements were successful with minimal complications

Team Size on Site

4-5 ACL crew, sub contractors on site (4 people) & traffic control

Sustainability Certifications

Environmental

Construction progress 1
Construction progress 2

Subcontractor(s)

N/A