Hudson Hope Provincial Park Upgrades

Hudson Hope, B.C

CLIENT
District of Hudson Hope
Parks infrastructure and site amenity installation
VALUE
$300K
DURATION
Duration: August - September 2023

Project Scope

  • Installation of multiple outhouses.
  • Post and beam picnic shelter
  • Fire ring
  • Bear Proof Containers
  • Information Shelter

Roles & Responsibilities

  • Preconstruction meeting with the Owner;
  • Weekly meetings and progress updates;
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered. Solutions provided as options when applicable;
  • Quality management updates and quality control check sheets of construction progress and material installs;
  • Coordination of subcontractors to complete project works;
  • Coordination of third-party utilities such as BC Hydro, Pacific Northern Gas, TELUS, Shaw, etc.;
  • Site inspections with the Owner; and,
  • Final walk through and completion of deficiencies in a timely manner.
Construction progress 1
PIP Concrete Pads for Picnic Shelter
Construction progress 2
Supply and Install Pre-built Outhouses

Subcontractor(s)

N/A