Project

Meziadin Pipe Push

Meziadin Junction, Highway 37

CLIENT
Dawson Road Maintenance
VALUE
$2.3M
DURATION
September 2025 - November 2025

Project Scope

West of Surprise Pit

  • Build access inlet side, create bypass pumping pad, entrance pit (trucking of spoil and supply of granular by DRM)
  • Build access outlet side, receiving pit, realign channel (trucking of spoil and supply of granular by DRM)
  • Rip Rap placement, inlet and outlet (supply/delivery by DRM)
  • Grout abandoned culvert
  • Bypass water pumping
  • Supply & install 60” x 36m pipe

Lakeview Corner

  • Build access inlet side, create bypass pumping pad, entrance pit (trucking of spoil and supply of granular by DRM)
  • Build access outlet side, receiving pit, realign channel (trucking of spoil and supply of granular by DRM)
  • Rip rap placement, inlet and outlet (supply/delivery by DRM)
  • Grout abandoned culvert
  • Bypass water pumping
  • Supply & install 72” x 45m pipe

Roles & Responsibilities

Challenge

Limited geology showing fill and rock formation, potential challenge in installation rate and risk of encountering boulders and large size rock

ACL Solution

Up size the gauge of the steel culvert in case structures were encountered

Sustainability Certifications

Environmental monitoring

Construction progress 1
Construction progress 2

Subcontractor(s)

The Casing Company, E.S. Construction

Let’s get your project off the ground!

From site preparation and underground utilities to road building and large-scale infrastructure work, our team will work with you to deliver practical solutions that align with your goals, timeline, and budget.

Start a Conversation
Share this on: