Project
Meziadin Pipe Push
Meziadin Junction, Highway 37
CLIENT
Dawson Road Maintenance
VALUE
$2.3M
DURATION
September 2025 - November 2025
Project Scope
West of Surprise Pit
- Build access inlet side, create bypass pumping pad, entrance pit (trucking of spoil and supply of granular by DRM)
- Build access outlet side, receiving pit, realign channel (trucking of spoil and supply of granular by DRM)
- Rip Rap placement, inlet and outlet (supply/delivery by DRM)
- Grout abandoned culvert
- Bypass water pumping
- Supply & install 60” x 36m pipe
Lakeview Corner
- Build access inlet side, create bypass pumping pad, entrance pit (trucking of spoil and supply of granular by DRM)
- Build access outlet side, receiving pit, realign channel (trucking of spoil and supply of granular by DRM)
- Rip rap placement, inlet and outlet (supply/delivery by DRM)
- Grout abandoned culvert
- Bypass water pumping
- Supply & install 72” x 45m pipe
Roles & Responsibilities
Challenge
Limited geology showing fill and rock formation, potential challenge in installation rate and risk of encountering boulders and large size rock
ACL Solution
Up size the gauge of the steel culvert in case structures were encountered
Sustainability Certifications
Environmental monitoring
Subcontractor(s)
The Casing Company, E.S. Construction