Project
Airport Runway Reconstruction and Taxiway Extension
Whitehorse International Airport, Yukon
CLIENT
Yukon Government; A.C.L. Subcontractor to Prime Contractor Flatiron Corporation
VALUE
$6.9M (A.C.L. Portion)
DURATION
June 2023 – April 2025
Project Scope
- Site preparation, stripping materials, trenching and benching for line installation
- Installation of sanitary and water lines, manholes, catch basins, and valving within trenches up to 7m in depth
- Tie in with new and existing services
- Backfilling materials
- Compaction of material and testing
- Finish grades with soil and seeding
Roles & Responsibilities
- Pre-construction meeting with the Owner & Field Engineer
- Weekly meetings and progress updates
- Updates when required to the Owner regarding technical or site issues or discrepancies encountered, solutions provided if required
- Diligently coordinating deliveries and supply orders due to lack of specialty support in Whitehorse area
- Quality management updates of construction progress and material installs
- Coordination of subcontractors to complete project works
- Coordination of third-party utilities
- Interface with other subtrades on site
- Site inspections with the Owner and Field Engineer
Subcontractor(s)
N/A