Project

Peterson’s Crossing Slide Repairs

Fort St. John, BC

CLIENT
Dawson Road Maintenance / Ministry of Transportation and Infrastructure (MoTI)
VALUE
$500K
DURATION
August 2023 - September 2023

Project Scope

  • Constructed to BC Hydro Specifications
  • Slope stabilization using EPS foam blocks
  • Site clearing and grubbing; Type D organic stripping
  • Excavation for riprap pad at gully inlet
  • Install three multi-tiered gabion structures, non-woven geotextile and bituminous membranes to prevent further erosion in streambed
  • Supply and place two 25 kg riprap diversion ditch blocks and supply and place one 50 kg and one 100 kg diversion channel
  • Abandon 800 mm culvert – infill with grout; supply and install 750 mm CSP Culvert
  • Regrade ditches and spillways
  • Remove concrete roadside barriers and chain link fence at project initiation and replace at project completion
  • Supply and place erosion matting and reseed

Roles & Responsibilities

  • Preconstruction meeting with the Owner
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
  • Quality management updates and quality control check sheets of construction progress and material installs
  • Coordination of subcontractors to complete project works
  • Coordination of third-party utilities such as BC Hydro, Pacific Northern Gas, TELUS, Shaw, etc.
  • Site inspections with the Owner
  • Final walk through after completion
Construction progress 1
Construction progress 2

Subcontractor(s)

N/A