KM155 Slope Stabilization
KM155 Alaska Highway
CLIENT
PSPC
VALUE
$2.3M
DURATION
January 2021 – March 2021
Project Scope
- Clear & strip site
- Common excavation
- Build French Drain
Roles & Responsibilities
- Preconstruction meeting with the Owner & Field Engineer
- Weekly meetings and progress updates
- Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
- Quality management updates of construction progress and material installs
- Coordination of subcontractors to complete project works
- Coordination of third-party utilities
- Site inspections with the Owner and Field Engineer
Challenge
The pavement started to subside due to a spring in the shoulder of the highway
ACL Solution
Create a French drain and Stabilize slope along Alaska Highway
Subcontractor(s)
N/A