Inga Lake Intersection Improvements

Inga Lake, BC

CLIENT
Public Works and Government Services Canada
Civil road construction & intersection upgrades
VALUE
$3.2M
DURATION
August 2021 to September 2022.

Project Scope

  • British Columbia Ministry of Transportation and Infrastructure Specifications, 2016 Edition.
  • Clearing and stripping;
  • Common excavation and embankment cut to fill, prepare subgrade c/w geotextile and geogrid;
  • Construct road structure and gravel shoulder c/w granular hauling and compaction;
  • Removal of old culvert and installation of Aluminized CSP Culvert, complete with riprap armoring;
  • Cold milling of asphalt and placement of hot mix asphalt concrete pavement surface with rumble strips;
  • Pavement markings and intersection traffic signage; and,
  • Revegetation – topsoil and seeding.

Roles & Responsibilities

  • Preconstruction meeting with the Owner & Field Engineer;
  • Weekly meetings and progress updates;
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered. Solutions provided as options when applicable;
  • Quality management updates of construction progress and material installs.
  • Coordination of subcontractors to complete project works;
  • Coordination of third-party utilities such as BC Hydro, Pacific Northern Gas, Northwestel, Shaw, North River Midstream, etc.;
  • Site inspections with the Owner and Field Engineer; and,
  • Final walk through and completion of deficiencies in a timely manner.
Construction progress 1
Inga Lake Intersection asphalt paving in progress.
Construction progress 2
Inga Lake Intersection completed.

Subcontractor(s)

  • Paving – DGS Astro Paving Ltd.
  • Line painting – Lazer Pavement Solutions
  • Materials Testing of Aggregates – Parkland Geo