Bluegrave Scour Repair

Bluegrave Bridge – Mile 95 Alaska Highway

CLIENT
DRM
VALUE
$300K
DURATION
July 2025 – Oct 2025

Project Scope

  • Scour Repair
  • Isolation & Dewatering

Roles & Responsibilities

Challenge

Had to set meter bags into the creek with a crane to establish the isolation, reestablish shoulder along the embankment that had eroded.  Install rip rap to shore and protect the new embankment fill

Team Size on Site

Superintendent, two operators, 3 labourers, medic

Sustainability Certifications

Environmental monitoring daily

Job completely safely and on schedule

Construction progress 1
Construction progress 2

Subcontractor(s)

N/A