Project
Blueberry Bridge Scour and Erosion Mitigation
Fort St. John, BC
CLIENT
Dawson Road Maintenance/ Ministry of Transportation and Infrastructure (MoTI)
VALUE
$400K
DURATION
October-November 2022; July-August 2023
Project Scope
- Constructed to BC MoTI 2020 Standard Specifications for Highway Construction
- Clearing of vegetation onsite
- Prepare equipment with bio lubricants to be working in-steam
- Installation of poly lined meter bags for stream isolation to conduct required fish salvage
- Excavate sloughed materials from erosion caused by flood in 2017 along with gullying and erosion also occurring on the embankment and around upslope piers from highway runoff
- Placement of riprap around piers to prevent further erosion
- Installation of grout around base of some piers for additional erosion support
- Restoration and revegetation of site
Roles & Responsibilities
- Preconstruction meeting with the Owner
- Weekly meetings and progress updates
- Updates when required to the Owner regarding technical or site issues or discrepancies encountered. Solutions provided as options when applicable
- Quality management updates and quality control check sheets of construction progress and material installs
- Coordination of subcontractors to complete project works
- Site inspections with the Owner
- Final walk through and completion of deficiencies in a timely manner
Subcontractor(s)
Rivers Sand & Gravel.