Blueberry Bridge Scour and Erosion Mitigation

Fort St. John, BC

CLIENT
Dawson Road Maintenance/ Ministry of Transportation and Infrastructure (MoTI)
In-stream bridge protection and erosion control
VALUE
$0.4M
DURATION
October-November 2022; July-August 2023

Project Scope

  • Constructed to BC MoTI 2020 Standard Specifications for Highway Construction.
  • Clearing of vegetation onsite.
  • Prepare equipment with bio lubricants to be working in-steam.
  • Installation of poly lined meter bags for stream isolation to conduct required fish salvage.
  • Excavate sloughed materials from erosion caused by flood in 2017 along with gullying and erosion also occurring on the embankment and around upslope piers from highway runoff.
  • Placement of riprap around piers to prevent further erosion.
  • Installation of grout around base of some piers for additional erosion support.
  • Restoration and revegetation of site.

Roles & Responsibilities

  • Preconstruction meeting with the Owner;
  • Weekly meetings and progress updates;
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered. Solutions provided as options when applicable;
  • Quality management updates and quality control check sheets of construction progress and material installs;
  • Coordination of subcontractors to complete project works;
  • Coordination of third-party utilities such as BC Hydro, Pacific Northern Gas, TELUS, Shaw, etc.;
  • Site inspections with the Owner; and,
  • Final walk through and completion of deficiencies in a timely manner.
Construction progress 1
Placement of riprap
Construction progress 2
Grout placement of pier abutment.

Subcontractor(s)

Rivers Sand & Gravel.