Canfor Aeration Lagoon Removal

Taylor, BC

CLIENT
Canfor
VALUE
$600K
DURATION
August 2023 - September 2023

Project Scope

  • Removal of sludge in the bottom of lagoon
  • Removal of aeration lagoon
  • Hauling of materials from site to landfill
  • Final grading and clean up

Roles & Responsibilities

  • Preconstruction meeting with the Owner
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
  • Quality management updates and quality control check sheets of construction progress and material installs
  • Coordination of subcontractors to complete project works
  • Site inspections with the Owner
Construction progress 1
Construction progress 2

Subcontractor(s)

N/A