Project

ATCO – Leach Field

Site C Dam

CLIENT
ATCO Two Rivers
VALUE
$350K
DURATION
October 2020 – June 2023

Project Scope

  • Site preparation, stripping materials and trenching
  • Installation of sanitary lines, manholes and valving within trenches up to 2m in depth
  • Tie in utilities with new and existing services
  • Haul drain rock to site from gravel pit
  • Backfilling materials
  • Compaction of materials and compaction testing
  • Finish grades with soil and seeding

Roles & Responsibilities

  • Preconstruction meeting with the Owner
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions when required
  • Coordinating deliveries and supply orders
  • Quality management updates of construction progress and material installs
  • Coordination of third-party utilities
  • Interface with other subtrades on site
  • Site inspections with the Owner
Construction progress 1
Sani Manifold RE&RE
Construction progress 2
Leachfield RE&RE and Backfill/Contour

Subcontractor(s)

D. Bauer

Sani Manifold RE&RE
Sani Manifold Heat & Hoard for RE&RE
Leachfield RE&RE and Backfill/Contour
Reestablish Drainage around Leachfield