BC Hydro PRES Transmission Line

Fort St. John, BC

CLIENT
BC Hydro
VALUE
$5.2M
DURATION
June 2018 - September 2019

Project Scope

  • Build a portion of the transmission line that will run from the future Site C Substation near Fort St. John to the existing Groundbirch Substation
  • Trenching and benching for line installation
  • Transmission Tower Pad Construction

Roles & Responsibilities

  • Pre-Construction meetings with owners and engineers
  • Weekly meetings & progress updates
  • Coordinating deliveries and supply orders
  • Site inspections with owners and engineers

Challenge

Job was quite spread out over a vast area, many points of access along linear roadway

Highlight / Achievement

ACL’s first large scale project that put us on the civil construction map

Construction progress 1
Construction progress 2

Subcontractor(s)

N/A