KM155 Slope Stabilization

KM155 Alaska Highway

CLIENT
PSPC
VALUE
$2.3M
DURATION
January 2021 – March 2021

Project Scope

  • Clear & strip site
  • Common excavation
  • Build French Drain

Roles & Responsibilities

  • Preconstruction meeting with the Owner & Field Engineer
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
  • Quality management updates of construction progress and material installs
  • Coordination of subcontractors to complete project works
  • Coordination of third-party utilities
  • Site inspections with the Owner and Field Engineer

Challenge

The pavement started to subside due to a spring in the shoulder of the highway

ACL Solution

Create a French drain and Stabilize slope along Alaska Highway

 

 

Construction progress 1
Construction progress 2

Subcontractor(s)

N/A