Project

Farrell Creek Pipe Installation

Highway 29

CLIENT
Dawson Road Maintenance/ Ministry of Transportation and Infrastructure
VALUE
$50K
DURATION
July 2023

Project Scope

  • Constructed to BC MoTI 2020 Standard Specifications for Highway Construction
  • Site clearing and grubbing
  • Type D organic stripping, onsite re-use or disposal
  • Excavation of slide area for installment
  • Place gravels for road structure and compact to specifications
  • Regrade ditches and ensure positive drainage away from slide area
  • Place jersey barriers along road edge

Roles & Responsibilities

  • Preconstruction meeting with the Owner
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
  • Quality management updates and quality control check sheets of construction progress and material installs
  • Coordination of subcontractors to complete project works
  • Site inspections with the Owner
Construction progress 1
Construction progress 2

Subcontractor(s)

N/A