Project
Rehabilitation of Bridge Culvert Number 6 Crossing
Toad River, BC
CLIENT
Public Works and Government Services Canada
VALUE
$2.1M
DURATION
September 2022 - December 2022
Project Scope
- Construct to British Columbia Ministry of Transportation and Infrastructure Specifications, 2020 Edition
- Line existing 3900 mm diameter SPCSP by 39.8 m invert length with a 3300 mm CSP by 53 m invert length and grout in place
- Concrete collars installed at inlet and outlet ends of 3300 mm CSP
- 1000 kg rip rap armoring place at outlet end and 800 kg riprap armoring placed at inlet end
- Install precast concrete block wall at outlet end
- Completed side slope improvements to reinforce slope integrity at outlet end and place 150 mm granular cover
- Place topsoil and hydroseed
Roles & Responsibilities
- Preconstruction meeting with the Owner, Field Engineer and Environmental Consultant
- Weekly meetings and progress updates
- Updates when required to the Owner regarding technical or site issues or discrepancies encountered, solutions provided if required
- Quality management updates of construction progress and material installs
- Coordination of subcontractors to complete project works
- Coordination of third-party utilities such as BC Hydro, Pacific Northern Gas, Northwestel, Shaw, etc.
- Site inspections with the Owner
Subcontractor(s)
Tom’s Construction Ltd, Parkland GEO