Inga Lake Intersection Improvements

Inga Lake, BC

CLIENT
Public Works and Government Services Canada
VALUE
$3.2M
DURATION
August 2021 - September 2022

Project Scope

  • Clearing and stripping site
  • Common excavation and embankment cut to fill, prepare subgrade with geotextile and geogrid
  • Construct road structure and gravel shoulder with granular hauling and compaction
  • Removal of old culvert and installation of Aluminized CSP Culvert, complete with riprap armoring
  • Cold milling of asphalt and placement of hot mix asphalt concrete pavement surface with rumble strips
  • Pavement markings and intersection traffic signage
  • Revegetation – topsoil and seeding

Roles & Responsibilities

  • Preconstruction meeting with the Owner & Field Engineer
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, provide solutions if required
  • Quality management updates of construction progress and material installs
  • Coordination of subcontractors to complete project works
  • Coordination of third-party utilities
  • Site inspections with the Owner and Field Engineer
Construction progress 1
Construction progress 2

Subcontractor(s)

DGS Astro Paving Ltd, Lazer Pavement Solutions, Parkland GEO