Rehabilitation of Bridge Culvert Number 6 Crossing

Toad River, BC

CLIENT
Public Works and Government Services Canada
VALUE
$2.1M
DURATION
September 2022 - December 2022

Project Scope

  • Construct to British Columbia Ministry of Transportation and Infrastructure Specifications, 2020 Edition
  • Line existing 3900 mm diameter SPCSP by 39.8 m invert length with a 3300 mm CSP by 53 m invert length and grout in place
  • Concrete collars installed at inlet and outlet ends of 3300 mm CSP
  • 1000 kg rip rap armoring place at outlet end and 800 kg riprap armoring placed at inlet end
  • Install precast concrete block wall at outlet end
  • Completed side slope improvements to reinforce slope integrity at outlet end and place 150 mm granular cover
  • Place topsoil and hydroseed

Roles & Responsibilities

  • Preconstruction meeting with the Owner, Field Engineer and Environmental Consultant
  • Weekly meetings and progress updates
  • Updates when required to the Owner regarding technical or site issues or discrepancies encountered, solutions provided if required
  • Quality management updates of construction progress and material installs
  • Coordination of subcontractors to complete project works
  • Coordination of third-party utilities such as BC Hydro, Pacific Northern Gas, Northwestel, Shaw, etc.
  • Site inspections with the Owner
Construction progress 1
Construction progress 2

Subcontractor(s)

Tom’s Construction Ltd, Parkland GEO

Culvert replacement ACL Construction
Culvert replacement ACL Construction
Culvert replacement ACL Construction
Culvert replacement ACL Construction
Culvert replacement ACL Construction