BC Hydro PRES Transmission Line

Fort St. John, BC

CLIENT
BC Hydro
VALUE
$5.2M
DURATION
June 2018 - September 2019

Project Scope

  • Build a portion of the transmission line that will run from the future Site C Substation near Fort St. John to the existing Groundbirch Substation
  • Trenching and benching for line installation
  • Transmission Tower Pad Construction

Roles & Responsibilities

  • Pre-Construction meetings with owners and engineers
  • Weekly meetings & progress updates
  • Coordinating deliveries and supply orders
  • Site inspections with owners and engineers

Challenge

Job was quite spread out over a vast area, many points of access along linear roadway

Highlight / Achievement

ACL’s first large scale project that put us on the civil construction map

Construction progress 1
Construction progress 2

Subcontractor(s)

N/A

BC Hydro PRES Project ACL Construction Excavator Ditching
BC Hydro PRES Project Land Clearing ACL Construction
BC Hydro PRES Project Land Clearing ACL Construction
BC Hydro PRES Project Land Clearing ACL Construction
Excavator loading a rock truck ACL Construction Fort St. John