Cecil Lake

Cecil Lake experienced a major slip on the North East portion of the hill so we were brought in to assess and complete a temporary detour for traffic. The slide incorporated the entire HWY, we stripped the site and unloaded the weight of materials from the site. We surveyed in a trail (based on old existing trail) and set road perimeters. Construction consisted of using on site materials and best construction practices. Sub base was placed, compacted and covered with aggregate materials. The hill, inlets and outlets were armored with rock for erosion control.